Virtual (Online) Public Meeting

May 13 – June 3, 2020

This virtual public meeting is an opportunity to gather public input on the proposed improvements at the I-70 interchange and proposed extension of Wentzville Parkway from Veterans Memorial Parkway to Interstate Drive.

Please review the project displays, facts, timeline, and comments form below.


Project Displays


Project Facts

  • Improve eastbound access to I-70 at Wentzville Parkway
  • Extend Wentzville Parkway from Veterans Memorial Parkway to Interstate Drive
  • Construct new bridge over Norfolk Southern Railroad to consolidate crossings
  • Improve safety by closing Wilmer Road at-grade crossing and evaluate potential future Hepperman Road crossing closure
  • Tentative construction: 2021-2023
  • Estimated total project cost: $11.1 million


Project Timeline

2011

Location Study Started

Location Study started to study alternative alignments for extension of Wentzville Parkway from I-70 to Wilmer Road

Public Meeting

One public meeting held on February 21, 2012, for the extension of Wentzville Parkway

2012
2013


Location Study Completed


Location Study Supplement

Study analyzed interchange and railroad crossing alternatives

2015 – 2016
2016

Public Meeting

Public meeting held Jan 21, 2016

Funding Secured

Federal and County funding secured for Interchange Improvements and extension of Wentzville Parkway from Veterans Memorial Parkway to Interstate Drive

2018
2019

Design Work on Interchange and Extension Starts

Virtual Public Meeting

Virtual public meeting conducted to gather feedback

May – June 2020
2020 – 2021

Right of Way Acquisition

Interchange Construction Starts

Construction of interchange improvements starts

2021
2022

Extension Construction Starts

Construction of Wentzville Parkway extension starts

Construction Complete

Spring 2023

Send Us Your Feedback